It started with a new master bedroom closet:
thus freeing the old closet to become a walk-in pantry off of the kitchen/breakfast area.
The kitchen was refreshed: old wallpaper was removed, new paint and trim was added, new floor replaced the original which had been damaged by fire and water:
With all of the new storage space complete, much of the living room and dining room furnishings were stored as the project moved to the middle third of the house. The wall between the living room and dining room was removed and the ceiling was raised in the dining room to match the existing ceiling in the living room:
The wall was a load-bearing wall, so it needed to be replaced with a beam in the attic. This beam was 14" high by 4" thick by 18' long:
With the wall gone, the space was really opened up:
Then came the entry wallpaper removal, the texturing, the painting, and the trim staining:
And the final electrical work:
Then the floor and baseboards were installed and we were left with a few details, such as replacing door hardware:
Finally, furniture is moved back and the decorating begins:
(Click on any picture to enlarge.)
Shortly after completion, we were able to to host an Easter dinner for 17 using the space that had been divided into the dining room and living room:
This dinner used three tables end-to-end, but for a couple of years we have had our eyes on a table with the flexibility to match the flexibility of this room! This table is five feet long, but we purchased fourteen one-foot leaves, so it can be extended to nineteen feet. (It can be purchased with up to eighteen leaves, but that would not fit even in this expanded room.)
We were blessed in this project with help from many friends, family, and contractors. We are happy to recommend the following contractors to anyone needing the types of services they provided to us:
| Framing, painting, staining | Terry Miller Miller Exterior Design 3619 Tanglewood Circle Dallas, TX 75234 972-484-8993 |
| Floor | Don Potash Custom Floors 10825 Plano Road Dallas, TX 75238 214.341.0310 |
| Roof | Jacobs Roofing PO Box 270201 Flower Mound, TX 75028 817.430.2932 |
| Table | Doug & Brenda Arter Amish Heirloom Furniture 35-37 East Main St. Norwalk, OH 44857 419.663.3736 |
Are you contemplating a remodeling project? Perhaps you would like to look at our timeline first:
| February 2000 | Visit NARI Show, choose three possible contractors. |
| March 2000 | Set up appointments with contractors to obtain estimates. |
| Summer 2000 | Start electrical work and the building of the closet. |
| October 2000 | Move out of kitchen and master suite; contractors finish building new pantry, mount new bath cabinets, sheetrock where needed, paint & trim east end of house. Flooring contractors install Pergo throughout east end. |
| February 2001 | Move furniture and decorations out of the center third of the house. Hang dust shields on doorways. Contractors knock out dining room wall and ceiling and replace it with a beam. |
| March 2001 | Sheetrocking begins; two weeks off and on to install new ceiling and partial wall, tape and bed, texture paint all walls, match wood staining, install new decorative beams and ceiling trim. |
| March 12, 2001 | Flooring contractors return; Pergo extended through center part of house. |
| March 15, 2001 | Remodelers return for final installation of baseboard and final inspection. Praise the Lord! |
| April 8, 2001 | Passover Seder meal for 15 in the new room! |
| April 15, 2001 | Easter Dinner for 17 in the new room! Praise the Lord for family, friends, our new space -- and for His promise: "I am the resurrection and the life. He who believes in Me will live, even though he dies." (John 11:25) |
| Summer, 2001 | Painting and installing shelves, baseboards, closet doors. |
| Fall, 2001 | Decorating: dining table, picture framing and hanging. |
| 2002 | Replace roof Final trim in closets and bathroom |